Rs 1.67 Crore a Year, from Staffing Decisions Made on Data

A knitted-fabric and garment operation reduced manpower cost by 11% over 15 months, delivering around Rs 1.67 crore annual savings.

Annual savings: Rs 1.67 Cr15-month engagement

Results Snapshot

Annual savings
Rs 1.67 Cr
Manpower cost
-11%
Balancing
Yamazumi applied
Flow
Cellular manufacturing

The Situation

Workforce allocation was governed by department habit, with limited time-study evidence to challenge legacy staffing.

Some machines ran underloaded while associated manning remained unchanged.

Recurring labor cost was visible in accounts but lacked operational cause visibility.

What We Did

We linked manpower to actual workload, not precedent, and redesigned flow where needed.

  • Executed department-wise time studies.
  • Applied Yamazumi balancing across stations.
  • Introduced cellular manufacturing to tighten movement and handoffs.
  • Decommissioned underutilized machines and associated excess manning.

The Results

Manpower cost reduced 11% over 15 months, translating to roughly Rs 1.67 crore annual savings.

The organization now makes workforce decisions on data, improving resilience through demand cycles.

Strategic Takeaway

  • The key staffing question is not how many people, but matched to what load.
  • Data-based staffing survives peak demand cycles better than intuition-based staffing.

Contact Gemba Concepts

Need Help Solving Similar Execution Gaps?

Connect with our consulting team to discuss your current operational challenge and the outcomes you want to achieve.

sales@gembaconcepts.com
India Offices | Serving India, Middle East, and Africa

Share This Article

Found this useful? Share it with your team and peers.

Email UsWhatsApp